|
|
Table of Contents: Project Management Jokes
Project Management Truisms
1. It
takes one woman nine months to have a baby. It cannot be done in one month by
impregnating nine women.
2. Nothing is impossible for the person who doesn't have to do it.
3. You can con a sucker into committing to an impossible deadline, but you
cannot con him into meeting it.
4. At the heart of every large project is a small project trying to get out.
5. The more desperate the situation the more optimistic the situatee.
6. A problem shared is a buck passed.
7. A change freeze is like the abominable snowman: it is a myth and would melt
anyway when heat is applied.
8. A user will tell you anything you ask, but nothing more.
9. Of several possible interpretations of a communication, the least convenient
is the correct one.
10. What you don't know hurts you
11. There's never enough time to do it right first time but there's always
enough time to go back and do it again.
12. The bitterness of poor quality lasts long after the sweetness of making a
date is forgotten.
13. I know that you believe that you understand what you think I said, but I am
not sure you realise that what you heard is not what I meant.
14. What is not on paper has not been said.
15. A little risk management saves a lot of fan cleaning.
16. If you can keep your head while all about you are losing theirs, you haven't
understood the plan.
17. If at first you don't succeed, remove all evidence you ever tried.
18. Feather and down are padding, changes and contingencies will be real events.
19. There are no good project managers - only lucky ones.
20. The more you plan the luckier you get.
21. A project is one small step for the project sponsor, one giant leap for the
project manager.
22. Good project management is not so much knowing what to do and when, as
knowing what excuses to give and when.
23. If everything is going exactly to plan, something somewhere is going
massively wrong.
24. Everyone asks for a strong project manger - when they get one, they don't
want one.
25. Overtime is a figment of the naïve project manager's imagination.
26. Quantitative project management is for predicting cost and schedule overruns
well in advance.
27. The sooner you begin coding the later you finish.
28. Metrics are learned men's excuses.
29. For a project manager, overruns are as certain as death and taxes.
30. Some projects finish on time in spite of project management best practices.
31. Fast - cheap - good - you can have any two.
32. There is such a thing as an unrealistic timescale.
33. The project would not have been started if the truth had been told about the
cost and timescale.
34. A two-year project will take three years; a three-year project will never
finish.
35. When the weight of the project paperwork equals the weight of the project
itself, the project can be considered complete.
36. A badly planned project will take three times longer than expected - a
well-planned project only twice as long as expected.
37. Warning: dates in a calendar are closer than they appear to be.
38. Anything that can be changed will be changed until there is no time left to
change anything.
39. There is no such thing as scope creep, only scope gallop.
40. A project gets a year late one day at a time.
41. If you're 6 months late on a milestone due next week but really believe you
can make it, you're a project manager.
42. No project has ever finished on time, within budget, to requirements.
43. Yours won't be the first to.
44. Activity is not achievement.
45. Managing IT people is like herding cats.
46. If you don't know how to do a task, start it, then ten people who know
less than you will tell you how to do it.
47. If you don't plan, it doesn't work. If you do plan, it doesn't work either.
Why plan!
48. The person who says it will take the longest and cost the most is the only
one with a clue how to do the job.
49. The sooner you get behind schedule, the more time you have to make it up.
50. The nice thing about not planning is that failure comes as a complete
surprise rather than being preceded by a period of worry and depression.
51. Good control reveals problems early - which only mean you'll have longer to
worry about them.
Glossary of Planning Terms
This is a glossary of regularly used terms and phrases associated with
project planning, compiled to ensure that all Project and Programme members have
a common understanding of the complicated jargon used by the planning team to
confuse and delude Project Managers, Programme Managers and anyone involved in
signing timesheets.
- Critical Path Analysis
- Shortest route between work and the local pub
- Barchart
- Price List at the local pub
- Float
- Remaining Beer kitty
- End Stage Assessment
- Who's round is it next
- Mid Stage Assessment
- If I slow up drinking Len will get the next round in
- Progress Report
- How much beer left in the glass?
- Plan
- Blank sheet of paper to carry round
- Milestone
- Paul buys a round
- PERT Chart
- Grading of best looking girls in the pub
- Time Analysis
- Can we get another pint in before last orders?
- Earned Value
- The Pay Cheque
- BCWS
- Beer Consumption When Sober
- BCWP
- Beer Consumption When Pissed
- ACWP
- Always Check When Paid
- Timesheet
- Is that the time?!!! oh sheeeet
- Slip
- Being first at the bar
- GANTT
- Get Absolutely Nowhere Telling Truth
A Prayer for the Stressed
Grant me the serenity to accept the things I cannot change.
the courage to change the things I cannot accept,
and the wisdom to hide the bodies of those I had
to kill today because they got on my nerves.
And also, help me to be careful of the toes I step on
today as they may be connected to the feet I may have
to kiss tomorrow.
Help me to always give 100% at work....
12% on Monday
23% on Tuesday
40% on Wednesday
20% on Thursday
5% on Fridays
And help me to remember...
When I'm having a really bad day,
and it seems that people are trying to wind me up,
that it takes 42 muscles to frown, 28 to smile and
only 4 to extend my arm and smack someone in the mouth!
Motivation and Morale
Once upon a time, a British company and a Japanese company decided to have a
competitive boat race on the River Thames. The Japanese won by a mile.
The British firm became very discouraged and morale sagged. Senior Management
decided that the reason for the crushing defeat had to be found and a project
team was set up to investigate the problem and recommend the appropriate action.
Their conclusion: the Japanese team had eight people rowing and one person
steering. The British team had one person rowing and eight people steering.
Senior Management immediately hired a consultant company to do a study of the
British team's structure. Millions of pounds and several months later they
concluded that too many people were steering and not enough rowing.
To prevent losing to the Japanese next year, the team structure was changed
to four 'Steering Managers', three 'Senior Steering Managers' and one 'Executive
Steering Manager'. A performance and appraisal system was set up to give the
person rowing the boat more incentive to work harder and become a key performer.
The next year the Japanese won by two miles. The Executive Steering Manager
of the British companywas heard to say: "Next year that lazy SOB is going to
have to row a lot harder!" But his underlings laid off the rower for poor
performance, sold off the oars, cancelled all capital investment for new
equipment and halted development of a new boat. They gave high performance
awards to the consultants and distributed the money saved to Senior Management.
Decoding the Jargon
Here's a set of definitions to help you understand what those Checkpoint
Reports are really telling you !
- Essentially complete
- It's half done.
- We predict...
- We hope to God!
- Risk is high, but within acceptable ranges of risk
- 100:1 odds, or with 10 times over budget using 10 times the people we said
we'd employ.
- Potential show stopper.
- The team has updated their resumes.
- Serious but not insurmountable problems.
- It'll take a miracle...
- Basic agreement has been reached.
- The @##$%%'s won't even talk to us.
- Results are being quantified.
- We're massaging the numbers so they will agree with our conclusions.
- Task force to review.
- Seven people who are incompetent at their regular jobs have been loaned to
the project
- Not well defined at this time.
- Nobody's even thought about it.
- Still analysing the requirements.
- See previous answer.
- Not well understood.
- Now that we've thought about it, we don't want to think about it anymore.
- Requires further analysis and management attention.
- Totally out of control!
- Results are promising
- Turned power on and no smoke detected -- this time...
- Elements will be phased in gradually as the software interface matures
- It's late!
- Unacceptable stretching-out of the time scale
- It's late!
- Still in the early phase of the learning curve
- New
- The requirement was changed and the programme concluded
- Cancelled
- Experiencing transient malfunctions
- Going wrong
- Conceptually configured in several variations
- Modified
- A structured interface with the government on an inter-departmental basis
- Money!
Coding Monkeys
A tourist walked into a pet shop and was looking at the animals on display.
While he was there, another customer walked in and said to the shopkeeper, "I'll
have a C monkey please." The shopkeeper nodded, went over to a cage at the side
of the shop and took out a monkey. He fitted a collar and leash, handed it to
the customer, saying, "That'll be £5,000."
The customer paid and walked out with his monkey. Startled, the tourist went
over to the shopkeeper and said, "That was a very expensive monkey. Most of them
are only a few hundred pounds. Why did it cost so much?" The shopkeeper
answered, "Ah, that monkey can program in C - very fast, tight code, no bugs,
well worth the money."
The tourist looked at a monkey in another cage. "Hey, that one's even more
expensive! £10,000! What does it do?"
"Oh, that one's a C++ monkey; it can manage object-oriented programming,
Visual C++, even some Java. All the really useful stuff," said the shopkeeper.
The tourist looked around for a little longer and saw a third monkey in a
cage of its own. The price tag around its neck read £50,000. The tourist gasped
to the shopkeeper, "That one costs more than all the others put together! What
on earth does it do?"
The shopkeeper replied, "Well, I haven't actually seen it do anything, but it
says it's a project manager".
Phrases for appraisals
Short of an apt phrase for the annual appraisal of your staff? Try some of
these for size (reputedly from RN Officer Fitness Reports):
- His men would follow him anywhere, but only out of curiosity.
- I would not breed from this Officer.
- This Officer is really not so much of a has-been, but more of a definitely
won't-be.
- When she opens her mouth, it seems that this is only to change whichever
foot was previously in there.
- He has carried out each and every one of his duties to his entire
satisfaction.
- He would be out of his depth in a car park puddle.
- Technically sound, but socially impossible.
- This Officer reminds me very much of a gyroscope - always spinning around
at a frantic pace, but not really going anywhere.
- This young lady has delusions of adequacy.
- When he joined my ship, this Officer was something of a granny; since then
he has aged considerably.
- This Medical Officer has used my ship to carry his genitals from port to
port, and my officers to carry him from bar to bar.
- Since my last report he has reached rock bottom, and has started to dig.
- She sets low personal standards and then consistently fails to achieve
them.
- He has the wisdom of youth, and the energy of old age.
- This Officer should go far - and the sooner he starts, the better.
- In my opinion this pilot should not be authorised to fly below 250 feet.
- The only ship I would recommend this man for is citizenship.
- Works well when under constant supervision and cornered like a rat in a
trap
- This man is depriving a village somewhere of an idiot.
- Only occasionally wets himself under pressure.
Financial Obfuscation
Up against it on the costs front? Need to face the Project Board and
explain? This little (old) gem should help you better than saying
'supercalifragilisticexpialidocious'!
From evidence given by an MoD expert to the Commons Expenditure Committee
on the cost of the Multi-role combat aircraft (shows its age, eh - it's been
called the Tornado since 1971 ....)
"Although these costs are higher than the costs which were reported in
your previous paper, the fact that in the present development 3(A) phase which I
described we are keeping to these cost levels (and with most of these increases
in cost was associated a defined extension of the programme) has led the three
countries, even though they have not sought approval from their governments and
will not be seeking approval for this level of cost until the next stage has to
be authorised in a few months' time, to accept this as a realistic cost with a
well-defined programme, somewhat longer, as I said earlier, than the programme
to which the previous cost attached."
Phew! That helpful little thing in MS Word reckons that lot has a
Flesch-Kincaid reading ease of 0.0 (idea is to get 60-70/100) !
The Perfect Worker
An appraisal for the perfect worker:
1 Bob Smith, my assistant programmer, can always be found
2 hard at work in his cubicle. Bob works independently, without
3 wasting company time talking to colleagues. Bob never
4 thinks twice about assisting fellow employees, and he always
5 finishes given assignments on time. Often he takes extended
6 measures to complete his work, sometimes skipping coffee
7 breaks. Bob is a dedicated individual who has absolutely no
8 vanity in spite of his high accomplishments and profound
9 knowledge in his field. I firmly believe that Bob can be
10 classed as a high-caliber employee, the type which cannot be
11 dispensed with. Consequently, I duly recommend that Bob be
12 promoted to executive management, and a proposal will be
13 executed as soon as possible.
Addendum:
That idiot was standing over my shoulder while I wrote the report sent to you
earlier today. Kindly re-read only the odd numbered lines.
Interpreting Employment Ads
Having difficulty finding the right words to convey just what your project is
like when placing those recruitment advertisements? Here's a set of terms that
may help!
- Competitive Salary
- We remain competitive by paying less than our competitors.
- Join Our Fast Paced Company
- We have no time to train you.
- Casual Work Atmosphere
- We don't pay enough to expect that you will dress up.
- Must be Deadline Oriented
- You will be six months behind schedule on your first day.
- Some Overtime Required
- Some time each night, some time each weekend.
- Duties will vary
- Anyone in the office can boss you around.
- Must have an Eye for Detail
- We have no quality control.
- Seeking Candidates with a Wide Variety of Experience
- You are replacing three people who just quit in disgust.
- Problem Solving Skills a Must
- You are walking into a company in perpetual chaos. Your first task is to
find out what is going on.
- Requires Team Leadership Skills
- You will have the responsibilities of a manager without the pay or
respect.
- Good Communication Skills
- Management communicates poorly, so you have to figure out what they want
and do it.
- Self starter
- You will get absolutely no support from management or your co-workers.
- Fast paced environment
- We need somebody that can tolerate a slave driving type A manager.
- Highly motivated individual
- We want someone who will put in long hours without extra pay.
- Team player
- We need a lackey and a yes man with good organisational skills - our
system is in chaos and we need someone to bail us out.
- Some travel required
- You won't see your spouse or kids for 6 months.
- Flexible schedule
- You are free to set your own hours as long as you are at work from 7:30 to
5:30 Monday through Friday.
- Co-ordinate your work hours with your co-workers
- You'll be working second shift.
- Pay based on experience
- We'll hire the cheapest worker we can find.
- Stock options
- We can't afford to pay you what you're worth so we'll give you this
worthless paper.
- Company bonus plan
- Our company doesn't make a profit.
- Comp time
- We're going broke and can't afford to pay overtime.
- Excellent opportunity for advancement
- We canned the guy that would have been your boss, you'll be expected to do
his job too.
- Leadperson
- You'll be doing your manager's job.
- Review and pay rise every 6 months
- You will be underpaid, we'll throw you a bone occasionally so you don't
leave.
- Contract to direct
- We're too cheap to hire somebody with your experience, we'll bring you in
as a contractor in hopes that you will like working here and be willing to
work for less money.
Balloonists
A woman in a hot air balloon was lost. She reduced altitude and spotted a
man below. She descended a bit more and shouted:
"Excuse me, can you help? I promised a friend I would meet her an hour ago,
but I don't know where I am."
The man replied: "You are in a hot air balloon hovering approximately 30 feet
above alkali desert scrub habitat, 2.7 miles west of the Colorado River near one
of the remnant populations and spawning grounds of the razorback sucker."
"You must be a biologist" said the balloonist.
"I am," replied the man. "How did you know?"
"Well," answered the balloonist, "everything you told me is technically
correct, but I have no idea what to make of your information, and the fact is I
am still lost. Frankly, you've not been much help so far."
The man below responded: "You must be a project manager."
"I am," replied the balloonist, "but how did you know?"
"Well, said the man, "you don't know where you are or where you're going. You
have risen to where you are due to a large quantity of hot air. You made a
promise to someone that you have no idea how to keep, and you expect me to solve
your problem. The fact is, you are in exactly the same position you were in
before we met, but somehow it's now my fault!"
Monkeys
A tourist walked into a pet shop and was looking at the animals on display.
While he was there,another customer walked in and said to the shopkeeper, "I'll
have a C monkey please." The shopkeeper nodded, went over to a cage at the side
of the shop and took out a monkey. He fitted a collar and leash,handed to the
customer,saying, "That'll be $5,000."
The customer paid and walked out with his monkey. Startled,the tourist went over
to the shopkeeper and said,"That was a very expensive monkey. Most of them are
only a few hundred pounds. Why did it cost so much? "The shopkeeper answered,
"Ah,that monkey can program in C - very fast,tight code,no bugs,well worth the
money."
The tourist looked at a monkey in another cage. "Hey,that one's even more
expensive! $10,000! What does it do?"
"Oh,that one's a C++ monkey; it can manage object-oriented programming,Visual
C++, even some Java All the really useful stuff," said the shopkeeper.
The tourist looked around for a little longer and saw a third monkey in a cage
of its own. The price tag around its neck read $50,000.The tourist gasped to the
shopkeeper, "That one costs more than all the others put together! What on earth
does it do?"
The shopkeeper replied, "Well, I haven't actually seen it do anything, but it
says it's a project manager".
Software Development Cycle
- Programmer produces code he believes is bug-free.
- Product is tested. 20 bugs are found.
- Programmer fixes 10 of the bugs and explains to the testing department
that the other 10 aren't really bugs.
- Testing department finds that five of the fixes didn't work and
discovers 15 new bugs.
- Repeat three times steps 3 and 4.
- Due to marketing pressure and an extremely premature product
announcement based on overly-optimistic programming schedule, the product is
released.
- Users find 137 new bugs.
- Original programmer, having cashed his royalty check, is nowhere to be
found.
- Newly-assembled programming team fixes almost all of the 137 bugs, but
introduce 456 new ones.
- Original programmer sends underpaid testing department a postcard from
Fiji. Entire testing department quits.
- Company is bought in a hostile takeover by competitor using profits from
their latest release, which had 783 bugs.
- New CEO is brought in by board of directors. He hires a programmer to
redo program from scratch.
- Programmer produces code he believes is bug-free...
The Genie
As with all well run projects the Project Manager and his Technical Design
Authority and Chief Systems Analyst were having a lunch time stroll along the
beach when they happened on a small brass lamp. Well, you know the rest: they
rubbed it and the ever grateful genie appeared, but when confronted with the
three of them shared the traditional three wishes as one each.
The ever eager TDA claimed first go and requested a South Sea Island with
sweet music, swaying palm trees with matching supply of lei clad girls
delivering endless Tequila Sundowners. "No problem" said the Genie, and with a
quick flash and a cloud of blue smoke the TDA disappeared.
Then came the CSA, a much simpler chap, who merely wished to be locked in the
sample room of the Guinness St James' Brewery in Dublin with a guarantee of a
self-regenerating liver. "No problem" said the Genie, and with a quick flash and
a cloud of blue smoke the CSA disappeared.
Then came the Project Manager. "Simple!" said he. "I want those other two
back at their desks by 1:30."
Project Management Proverbs
- It takes one woman nine months to have a baby. It cannot be done in one
month by impregnating nine women.
- Nothing is impossible for the person who doesn't have to do it.
- You can con a sucker into committing to an impossible deadline, but you
cannot con him into meeting it.
- At the heart of every large project is a small project trying to get out.
- The more desperate the situation the more optimistic the situatee.
- A problem shared is a buck passed.
- A change freeze is like the abominable snowman: it is a myth and would
anyway melt when heat is applied.
- A user will tell you anything you ask, but nothing more.
- Of several possible interpretations of a communication, the least
convenient is the correct one.
- What you don't know hurts you
- There's never enough time to do it right first time but there's always
enough time to go back and do it again.
- The bitterness of poor quality lasts long after the sweetness of making a
date is forgotten.
- I know that you believe that you understand what you think I said, but I
am not sure you realise that what you heard is not what I meant.
- What is not on paper has not been said.
- A little risk management saves a lot of fan cleaning.
- If you can keep your head while all about you are losing theirs, you
haven't understood the plan.
- If at first you don't succeed, remove all evidence you ever tried.
- Feather and down are padding, changes and contingencies will be real
events.
- There are no good project managers - only lucky ones.
- The more you plan the luckier you get.
- A project is one small step for the project sponsor, one giant leap for
the project manager.
- Good project management is not so much knowing what to do and when, as
knowing what excuses to give and when.
- If everything is going exactly to plan, something somewhere is going
massively wrong.
- Everyone asks for a strong project manger - when they get them they don't
want them.
- Overtime is a figment of the naïve project manager's imagination.
- Quantitative project management is for predicting cost and schedule
overruns well in advance.
- The sooner you begin coding the later you finish.
- Metrics are learned men's excuses.
- For a project manager overruns are as certain as death and taxes.
- Some project finish on time in spite of project management best practices.
- Fast - cheap - good - you can have any two.
- There is such a thing as an unrealistic timescale.
- The project would not have been started if the truth had been told about
the cost and timescale.
- A two-year project will take three years, a three year project will never
finish.
- When the weight of the project paperwork equals the weight of the project
itself, the project can be considered complete.
- A badly planned project will take three times longer than expected - a
well planned project only twice as long as expected.
- Warning: dates in a calendar are closer than they appear to be.
- Anything that can be changed will be changed until there is no time left
to change anything.
- There is no such thing as scope creep, only scope gallop.
- A project gets a year late one day at a time.
- If you're 6 months late on a milestone due next week but really believe
you can make it, you're a project manager.
- No project has ever finished on time, within budget, to requirement
- Yours won't be the first to.
- Activity is not achievement.
- Managing IT people is like herding cats.
- If you don't know how to do a task, start it, then ten people who know
less than you will tell you how to do it.
- If you don't plan, it doesn't work. If you do plan, it doesn't work
either. Why plan!
- The person who says it will take the longest and cost the most is the only
one with a clue how to do the job.
- The sooner you get behind schedule, the more time you have to make it up.
- The nice thing about not planning is that failure comes as a complete
surprise rather than being preceded by a period of worry and depression.
- Good control reveals problems early - which only means you'll have longer
to worry about them.
- It's hard to remember your job is to drain the swamp when you're up to
your a--e in alligators.
Top 10 Reasons NOT to Use Project Management
10. Our customers really love us, so they don't care if our products are late
and don't work.
9. I know there is a well-developed project management body of knowledge, but I
can't find it under this mess on my desk.
8. All our projects are easy, and they don't have cost, schedule, and technical
risks anyway.
7. Organising to manage projects isn't compatible with our culture, and the last
thing we need around this place is change.
6. We aren't smart enough to implement project management without stifling
creativity and offending our technical geniuses.
5. We might have to understand our customers' requirements and document a lot of
stuff, and that is such a bother.
4. Project management requires integrity and courage, so they would have to pay
me extra.
3. Our bosses won't provide the support needed for project management; they want
us to get better results through magic.
2. We'd have to apply project management blindly to all projects regardless of
size and complexity, and that would be stupid.
1. We figure it's more profitable to have 50% overruns than to spend 10% on
project management to fix them.
The Plan - or how NOT to report progress .....
In the beginning was THE PLAN.
And then came The Assumptions.
And The Plan was without substance.
And The Assumptions were without form.
And darkness was upon the face of the Workers.
And they spoke among themselves, saying,
'It is a crock of s--t, it stinks.'
And the workers went unto their Supervisors, and said,
'It is a pail of dung, and none may abide the odour thereof.'
And the Supervisors went unto their Managers, saying
'It is a container of excrement, and it is very strong,
such that none may abide it.'
And the Managers went unto their Directors, saying,
'It is a vessel of fertiliser, and none may abide its strength.'
And the Directors spoke among themselves saying one to
another,
'It contains that which aids plant growth, and it is very strong.'
And the Directors went to the Vice-Presidents, saying unto
them,
'It promotes growth, and it is very powerful.'
And the Vice-Presidents went to the President, saying unto
him,
'This new plan will actively promote the growth and vigour of the company, with
powerful effects.'
And the President looked upon The Plan, and saw that it was
good.
And The Plan became policy.
And that is how S--t happens.
The Planning Miracle
What does a Project Manager DO?
Project Managers are a fortunate lot, for, as everyone knows, a project
manager has nothing to do; that is, except...
- To decide what is to be done;
- to tell somebody to do it;
- to listen to reasons why it should not be done,
- why it should be done by somebody else,
- or why it should be done in a different way;
- and to prepare arguments in rebuttal that shall be convincing and
conclusive.
And then:
- To follow up to see if the thing has been done;
- to discover that it has not been done;
- to enquire why it has not been done;
- to listen to excuses from the person who did not do it;
- and to think up arguments to overcome the excuses.
And then:
- To follow up a second time to see if the thing has been done;
- to discover that is has been done incorrectly;
- to point out how it shall be done;
- to conclude that as long as it has been done it might as well be left as
it is;
- to wonder if it is not time to get rid of the person who cannot do a thing
correctly;
- to reflect that in all probability any successor would be just as bad, or
worse.
And finally:
- To consider how much more simply and better the thing would have been done
had he done it himself in the first place;
- to reflect satisfactorily that if he had done it himself he would have
been able to do it right in 20 minutes and that as things turned out, he
himself spent two days trying to find out why it is that it has taken
somebody else three weeks to do it wrong.
- To realise that such an idea would have a very demoralising effect on the
project team, because it would strike at the very foundation of the belief
of all employees that a project manager has nothing to do.
(Thanks to Park Place Training Newsletter for that one ...)
The Buzz Phrase Generator
Stuck for a suitably meaningless expression to bamboozle that know-it-all
idiot who picked on you in that meeting the other day? Try this for size!
Pick any three-character number, then choose the appropriate combination of
words from each column in turn, e.g. 204 = Systematised Management Mobility.
Voilà! Your rival has to spend ten minutes working out what that means, while
you get on with your presentation in peace!
| |
Column 1 |
Column 2 |
Column 3 |
| 0 |
Integrated |
Management |
Options |
| 1 |
Total |
Organisational |
Flexibility |
| 2 |
Systemised |
Monitored |
Capability |
| 3 |
Parallel |
Reciprocal |
Mobility |
| 4 |
Functional |
Digital |
Mobility |
| 5 |
Responsive |
Logistical |
Concept |
| 6 |
Optimal |
Transitional |
Time-Phrase |
| 7 |
Synchronised |
Incremental |
Projection |
| 8 |
Compatible |
Third-generation |
Hardware |
| 9 |
Balanced |
Policy |
Contingency |
Project Manager Performance Appraisal
Here are some more well-turned phrases to help you judge your charges'
capabilities:
| Performance Factors |
Far Exceeds Requirements |
Exceeds Requirements |
Meets Requirements |
Needs some Improvement |
Does not meet Requirements |
| Quality |
Leaps tall buildings with a single bound |
Needs a running start to leap tall buildings |
Can only leap small buildings |
Crashes into buildings |
Cannot recognise buildings |
| Timeliness |
Is faster than a bullet |
Is as fast as a bullet |
Not quite as fast as a bullet |
Is as fast as a slow bullet |
Wounds self with gun |
| Initiative |
Is stronger than a locomotive |
Is stronger than a bull elephant |
Is stronger than a bull |
Shoots the bull |
Smells like a bull |
| Adaptability |
Walks on water consistently |
Walks on water in emergencies |
Washes with water |
Drinks water |
Passes water in emergencies |
| Communication |
Talks with God |
Talks with Angels |
Talks to self |
Argues with self |
Loses those arguments |
|